2008 Road Rehabiliatation
CIP7252 - 2008 Road Rehabiliatation
| Location: | West Davis Arterial streets |
|
| Status: | Complete | |
| Type: | Transportation | |
| Approved Budget: | 900,000 | |
| Project Manager: | Nancy McKee : nmckee@ci.davis.ca.us | |
| Design Consultant: | n/a | |
| Construction Contractor: | TBD | |
| Description: | CLICK ON "ATTACHMENTS" FOR PAVING SCHEDULE AND STREET LIST. Place a 1.5" asphalt overlay on various streets within the City of Davis. This year we will be concentrating on West Davis arterial and collector streets. By locating the project streets in the same area the contractor can be more efficient and we can stretch our dollars. This year the budget is primarily grant money that can only be spent on arterial streets. | |
| Additional Info: | The project also includes several curb ramps that will be upgraded to current ADA standards. This is a requirement of receiving the grant funds. The curb ramp work consists of approximately $100,000 of the budget. | |
| Last Update: | Monday Jan. 26, 2009 |
Project Details
- Updates
-
Project Status
- Tuesday September 30, 2008
The contractor is almost done except for some cleanup. - Thursday August 21, 2008
Click on "attachments" for the construction schedule. The contractor is currently working on the curb ramps. Street grinding and paving will begin on September 2, 2008. Russell Boulevard work will occur on Saturday Sept 6, Sunday Sept 7 and Sunday Sept. 14. - Thursday August 7, 2008
The contractor has started construction on the curb ramp portion of the contract. The grinding and paving will start in a few weeks. The construction schedule will be posted as soon as we receive it. - Monday July 7, 2008
Bids were opened on July 3. The apparent low bidder is American Engineering and Asphalt. The bid award will go to City Council on July 15, 2008. The estimated start date is July 28. - Thursday June 12, 2008
Caltrans approved the project on June 5. The project is out to bid and bids will be opened on July 3, 2008. If the project comes in over budget, some streets may be deleted from the contract. - Friday May 9, 2008
Caltrans approval is needed to go out to bid, due to the inclusion of grant money in the contract.
- Tuesday September 30, 2008
- Project Objectives
-
Project Objectives
- The condition of the entire City of Davis street system is tracked with the use of a computerized Pavement Management System. This program has a huge database, which logs all City streets and their condition. Field inspections are conducted every year on about 1/3 of the City streets to update the streets’ condition data. Using the inspection information, the streets’ condition (called the PCI, or Pavement Condition Index), is calculated by the computer program. The PCI is based on a scale of 1 to 100 (100 being a brand new street or one that has just been overlaid.) The City's objective is to maintain the average PCI of city streets at 70 or above. The current average PCI of the City streets is 71
- Pictures
-
Project Photos
- No project pictures
- Attachments
-
Project Attachments
- Construction Scedule
These are the construction dates for the streets to receive an overlay. There are two operations, grinding and paving.
- Street list
This attachment shows the street segments to receive an overlay
- Construction Scedule