2009 Road Rehabilitation
CIP7252 - 2009 Road Rehabilitation
| Location: | various streets |
|
| Status: | On Going | |
| Type: | Transportation | |
| Approved Budget: | 1,000,000 | |
| Project Manager: | Nancy McKee : nmckee@cityofdavis.org | |
| Design Consultant: | ||
| Construction Contractor: | ||
| Description: | Overlay major arterial streets within the City of Davis. The bulk of this project is funded by Stimulus money which can only be used on Arterial Streets | |
| Additional Info: | Preliminary Street List: Russell Boulevard between Anderson and A, Sycamore Lane between Russell and Covell, Anderson Road between Russell and Sunset, Grande Ave between F Street and Mercedes, Catalina bike lanes only between Alvarado and Anza north. | |
| Last Update: | Wednesday Oct. 14, 2009 |
Project Details
- Updates
-
Project Status
- Friday September 25, 2009
The paving is complete. The contractor will be working on raising the utility boxes and striping in the next few weeks. - Wednesday September 23, 2009
The paving work is done. The contractor will be adjusting the utility boxes in the street and finishing up the striping. - Wednesday July 15, 2009
This project is out to bid. The bid opening is July 16, 2009 at 2 pm - Monday May 18, 2009
The project is not yet out to bid pending Cal Trans approval for Federal Grant money.
- Friday September 25, 2009
- Project Objectives
-
Project Objectives
- No project objectives listed
- Pictures
-
Project Photos
- No project pictures
- Attachments
-
Project Attachments
- Street List
Attached is a list of streets that will be paved as a part of this contract. This project is funded with ARRA money and can only be spent on arterial or collector streets.
- Project Schedule
There will be MAJOR delays on Russell Boulevard from Anderson to A street during construction. Please seek alternate routes on the days specified on the attached schedule
- Street List