Public Works Facilities
CIP8512 - Public Works Facilities
| Location: | 1717 Fifth Street |
|
| Status: | On Going | |
| Type: | Facilities | |
| Approved Budget: | $2,079,932 | |
| Project Manager: | Mike Goodison, Assistant to the Director : mgoodison@ci.davis.ca.us | |
| Design Consultant: | Indigo Architects | |
| Construction Contractor: | Not in construction | |
| Description: | To rehabilitate and construct new facilities for Public Works operations and maintenance activities | |
| Additional Info: | Master Plan complete. Minimal attention at this time, but design to begin early summer 2002. | |
| Last Update: | Wednesday Oct. 14, 2009 |
Project Details
- Updates
-
Project Status
- Tuesday October 17, 2006
Final end blocks for the bins were placed in early August. See pics of completed project in pictures folder. - Tuesday June 6, 2006
Allied-West is back onsite and receiving the last deliveries of blocks. Bins should be completed very soon. Added pics in picture section. - Thursday April 20, 2006
Allied-West has completed the concrete slab and drainage sump. The first batch of concrete blocks to form the walls arrived yesterday. - Monday March 20, 2006
Corporation Yard Bins project was awarded to Allied-West Construction and work recently started. This project will add ten new concrete bins to house construction materials in the Corp Yard.
- Tuesday October 17, 2006
- Project Objectives
-
Project Objectives
- No project objectives listed
- Pictures
-
Project Photos
-
Click for larger image
Existing 30+ year old material bins to be demolished. -
Click for larger image
New material bins located in the east end of the yard made with interlocking concrete Ultrablocks. Bin walls are 7.5 feet high. -
Click for larger image
New material bins in use at the Public Works Corp Yard. -
Click for larger image
New material bins and rock drainage sump at the PW Corp Yard.
-