Sewer Trunkline Rehabilitation
CIP8166 - Sewer Trunkline Rehabilitation
| Location: | South of Wastewater Treatment Plant & N. of Co. Rd 30 |
|
| Status: | On Going | |
| Type: | Wastewater | |
| Approved Budget: | - | |
| Project Manager: | Terry Jue : tjue@cityofdavis.org | |
| Design Consultant: | - | |
| Construction Contractor: | D'Arcy & Harty Construction, San Francisco | |
| Description: | Clean and rehabilitate approximately 1 mile of the existing 48" sewer trunkline from County Road 30 to the south side of the Willow Slough Bypass. | |
| Additional Info: | ||
| Last Update: | Wednesday Oct. 14, 2009 |
Project Details
- Updates
-
Project Status
- Monday January 5, 2009
Construction was completed July-October 2008. - Tuesday July 15, 2008
Construction contract has been awarded to D'Arcy & Harty Construction out of San Francisco. Notice to Proceed was issued on June 30. - Tuesday May 6, 2008
Bid Opening has been changed to Thursday, May 15, 2 p.m. - Friday April 25, 2008
Plans and Specs approved on April 15. Project will bid on Tuesday, April 29. Bid Opening on May 13, 2:00 p.m. Construction window anticipated mid-June through September. - Tuesday March 18, 2008
Plans and specifications are nearly complete. Awaiting approval of Right of Entry or easement purchase to perform work. Project will bid in April or May. Construction window is May to October.
- Monday January 5, 2009
- Project Objectives
-